A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?


A.

Rolling wave planning


B.

Expert Judgement


C.

Decomposition


D.

Data analysis