PMI Certified Associate in Project Management (CAPM) CAPM Question # 104 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 104 Topic 11 Discussion

CAPM Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

Which of the following is an input to Control Scope?


A.

Project schedule


B.

Organizational process assets updates


C.

Project document updates


D.

Work performance information


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.