PMI Certified Associate in Project Management (CAPM) CAPM Question # 42 Topic 5 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 42 Topic 5 Discussion

CAPM Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?


A.

There is a cost underrun.


B.

There is a cost overrun.


C.

The project may not meet the deadline.


D.

The project is 20 days behind schedule.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.