Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 70 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 70 Topic 8 Discussion

CAPM Exam Topic 8 Question 70 Discussion:
Question #: 70
Topic #: 8

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?


A.

-8


B.

425


C.

1.4


D.

8


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.