Question #: 7
Topic #: 1

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?


A.

Project activities


B.

Work packages


C.

Planning packages


D.

Project deliverables