New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 112 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 112 Topic 12 Discussion

CAPM Exam Topic 12 Question 112 Discussion:
Question #: 112
Topic #: 12

Which two processes should be used to influence costs in the early stages of a project?


A.

Estimate Costs and Determine Budget


B.

Plan Cost Management and Estimate Activity Durations


C.

Control Quality and Control Costs


D.

Plan Stakeholder Engagement and Plan Communications Management


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.