Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 112 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 112 Topic 12 Discussion

CAPM Exam Topic 12 Question 112 Discussion:
Question #: 112
Topic #: 12

Organizations perceive risks as:


A.

events that will inevitably impact project and organizational objectives.


B.

the effect of uncertainty on their project and organizational objectives.


C.

events which could have a negative impact on project and organizational objectives.


D.

the negative impact of undesired events on their project and organizational objectives.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.