New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 113 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 113 Topic 12 Discussion

CAPM Exam Topic 12 Question 113 Discussion:
Question #: 113
Topic #: 12

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?


A.

What-if scenario analysis


B.

Simulation


C.

Alternatives analysis


D.

Reserve analysis


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.