Big 11.11 Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 149 Topic 15 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 149 Topic 15 Discussion

CAPM Exam Topic 15 Question 149 Discussion:
Question #: 149
Topic #: 15

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?


A.

Two


B.

Four


C.

Five


D.

Twelve


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.