PMI Certified Associate in Project Management (CAPM) CAPM Question # 151 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 151 Topic 16 Discussion

CAPM Exam Topic 16 Question 151 Discussion:
Question #: 151
Topic #: 16

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?


A.

Develop the feature as a parallel work package.


B.

Shorten the current work period and begin the new work.


C.

Ask a dedicated team member to complete it immediately.


D.

Prioritize it in the requirements list for the next work period.