Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 364 Topic 37 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 364 Topic 37 Discussion

CAPM Exam Topic 37 Question 364 Discussion:
Question #: 364
Topic #: 37

The following chart contains information about the tasks in a project.

CAPM Question 364

Based on the chart, what is the schedule performance index (5PI) for Task 4?


A.

0.83


B.

0.9


C.

1.11


D.

1.33


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.