PMI Certified Associate in Project Management (CAPM) CAPM Question # 365 Topic 37 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 365 Topic 37 Discussion

CAPM Exam Topic 37 Question 365 Discussion:
Question #: 365
Topic #: 37

Which statement about identification and engagement of stakeholders during a project is correct?


A.

Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.


B.

Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.


C.

Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.


D.

Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.