Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 389 Topic 39 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 389 Topic 39 Discussion

CAPM Exam Topic 39 Question 389 Discussion:
Question #: 389
Topic #: 39

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:


A.

Plan Human Resource Management.


B.

Acquire Project Team.


C.

Manage Project Team.


D.

Develop Project Team.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.