PMI Certified Associate in Project Management (CAPM) CAPM Question # 389 Topic 39 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 389 Topic 39 Discussion

CAPM Exam Topic 39 Question 389 Discussion:
Question #: 389
Topic #: 39

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?


A.

US$158,700


B.

US$172,500


C.

US$187,500


D.

US$245,600


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.