Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 95 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 95 Topic 10 Discussion

CAPM Exam Topic 10 Question 95 Discussion:
Question #: 95
Topic #: 10

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?


A.

Change request


B.

Risk response


C.

Risk management plan


D.

Lessons learned


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.