New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 95 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 95 Topic 10 Discussion

CAPM Exam Topic 10 Question 95 Discussion:
Question #: 95
Topic #: 10

For a stakeholder with low interest and high power, the project manager should:


A.

Monitor the stakeholder.


B.

Manage the stakeholder closely.


C.

Keep the stakeholder satisfied.


D.

Keep the stakeholder informed.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.