Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 384 Topic 39 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 384 Topic 39 Discussion

CAPM Exam Topic 39 Question 384 Discussion:
Question #: 384
Topic #: 39

What is the best tool to calculate the critical path on a project?


A.

Critical chain method


B.

Graphical evaluation and review technique (GERT) diagram


C.

Gantt chart


D.

Project network diagram


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.