PMI Certified Associate in Project Management (CAPM) CAPM Question # 384 Topic 39 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 384 Topic 39 Discussion

CAPM Exam Topic 39 Question 384 Discussion:
Question #: 384
Topic #: 39

Which tool should a project manager use to calculate cost variance for a project?


A.

Contingency analysis


B.

Review lessons learned from similar projects


C.

Expert judgment


D.

Actual cost


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.