Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 384 Topic 39 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 384 Topic 39 Discussion

CAPM Exam Topic 39 Question 384 Discussion:
Question #: 384
Topic #: 39

In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?


A.

The project is over budget and behind schedule.


B.

The project is over budget and ahead of schedule.


C.

The project is under budget and behind schedule.


D.

The project is under budget and ahead of schedule.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.