PMI Certified Associate in Project Management (CAPM) CAPM Question # 361 Topic 37 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 361 Topic 37 Discussion

CAPM Exam Topic 37 Question 361 Discussion:
Question #: 361
Topic #: 37

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?


A.

Follow organizational methodology and produce all required deliverables.


B.

Discuss the processes and deliverables needed to meet the project objectives with the team.


C.

Identify the processes and deliverables for only the current phase first.


D.

Integrate hybrid approach processes and deliverables to meet the short delivery timeline.