Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 362 Topic 37 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 362 Topic 37 Discussion

CAPM Exam Topic 37 Question 362 Discussion:
Question #: 362
Topic #: 37

The following chart contains information about the tasks in a project.

CAPM Question 362

Based on the chart, what is the cost performance index (CPI) for Task 2?


A.

0.8


B.

1


C.

1.25


D.

1.8


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.