Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 274 Topic 28 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 274 Topic 28 Discussion

CAPM Exam Topic 28 Question 274 Discussion:
Question #: 274
Topic #: 28

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?


A.

0.88


B.

1.12


C.

0.58


D.

1.58


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.