New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 274 Topic 28 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 274 Topic 28 Discussion

CAPM Exam Topic 28 Question 274 Discussion:
Question #: 274
Topic #: 28

Which of the following is used as an input to prepare a cost management plan?


A.

Expert judgment


B.

Lessons learned


C.

Cost estimates


D.

Project management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.