PMI Certified Associate in Project Management (CAPM) CAPM Question # 274 Topic 28 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 274 Topic 28 Discussion

CAPM Exam Topic 28 Question 274 Discussion:
Question #: 274
Topic #: 28

A project manager should document the escalation path for unresolved project risks in the:


A.

Change control plan


B.

Stakeholder register


C.

Risk log


D.

Communications management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.