Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 268 Topic 27 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 268 Topic 27 Discussion

CAPM Exam Topic 27 Question 268 Discussion:
Question #: 268
Topic #: 27

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:


A.

a control chart.


B.

baseline.


C.

Create WBS.


D.

decomposition.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.