Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 259 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 259 Topic 26 Discussion

CAPM Exam Topic 26 Question 259 Discussion:
Question #: 259
Topic #: 26

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?


A.

Diversity background


B.

Stakeholder's relationships


C.

Technical expertise


D.

Knowledge management


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.