PMI Certified Associate in Project Management (CAPM) CAPM Question # 259 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 259 Topic 26 Discussion

CAPM Exam Topic 26 Question 259 Discussion:
Question #: 259
Topic #: 26

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?


A.

Cost variance (CV)


B.

Cost performance index (CPI)


C.

Budget at completion (BAC)


D.

Variance at completion (VAC)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.