PMI Certified Associate in Project Management (CAPM) CAPM Question # 168 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 168 Topic 17 Discussion

CAPM Exam Topic 17 Question 168 Discussion:
Question #: 168
Topic #: 17

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?


A.

The customer and functional managers


B.

The risk owners and stakeholders


C.

The sponsors and stakeholders


D.

The project management team


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.