Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 168 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 168 Topic 17 Discussion

CAPM Exam Topic 17 Question 168 Discussion:
Question #: 168
Topic #: 17

When cost variance is negative and schedule variance is positive, the project is:


A.

under budget and behind schedule.


B.

over budget and ahead of schedule.


C.

on schedule.


D.

complete; all planned values have been earned.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.