Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 153 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 153 Topic 16 Discussion

CAPM Exam Topic 16 Question 153 Discussion:
Question #: 153
Topic #: 16

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?


A.

-700


B.

-200


C.

200


D.

500


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.