Question #: 330
Topic #: 34

The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?


A.

Cultural norms, roles and responsibilities, and organizational chart


B.

Assumption logs, resource calendars and training schedule


C.

Communication guidelines, conflict resolution process, and team agreements


D.

Company policies, recognition plan, and roles and responsibilities