New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 302 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 302 Topic 31 Discussion

CAPM Exam Topic 31 Question 302 Discussion:
Question #: 302
Topic #: 31

Which of the following is an input to Control Scope?


A.

Project schedule


B.

Organizational process assets updates


C.

Project document updates


D.

Work performance information


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.