PMI Certified Associate in Project Management (CAPM) CAPM Question # 342 Topic 35 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 342 Topic 35 Discussion

CAPM Exam Topic 35 Question 342 Discussion:
Question #: 342
Topic #: 35

At which stage of team development do members begin to work together, adjust work habits, and trust each other?


A.

Forming


B.

Storming


C.

Norming


D.

Performing