PMI Certified Associate in Project Management (CAPM) CAPM Question # 97 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 97 Topic 10 Discussion

CAPM Exam Topic 10 Question 97 Discussion:
Question #: 97
Topic #: 10

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:


A.

Determine Budget.


B.

Baseline Budget.


C.

Control Costs.


D.

Estimate Costs.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.