PMI Certified Associate in Project Management (CAPM) CAPM Question # 71 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 71 Topic 8 Discussion

CAPM Exam Topic 8 Question 71 Discussion:
Question #: 71
Topic #: 8

A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints. Which elements are included in the DSDM framework?


A.

Cost, requirements, schedule, and outputs


B.

Time, integration, cost, and deliverables


C.

Schedule, risk, integration, and features


D.

Cost, time, quality, and functionality


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.