PMI Certified Associate in Project Management (CAPM) CAPM Question # 73 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 73 Topic 8 Discussion

CAPM Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

The total of the planned value (PV) is also known as:


A.

work breakdown structure (WBS).


B.

schedule target.


C.

performance measurement baseline (PMB).


D.

earned value baseline.