PMI Certified Associate in Project Management (CAPM) CAPM Question # 73 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 73 Topic 8 Discussion

CAPM Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.

How can the manager document the business value for the Portfolio Steering Committee?


A.

Conduct a feasibility study to determine the business impact of the new product.


B.

Execute a market study for similar products and demonstrate a market need.


C.

Create a presentation outlining the business benefits of the new product.


D.

Prepare a benefits management plan to capture target benefits and strategic alignment.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.