PMI Certified Associate in Project Management (CAPM) CAPM Question # 50 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 50 Topic 6 Discussion

CAPM Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

The progressive detailing of the project management plan is called:


A.

expert judgment.


B.

rolling wave planning.


C.

work performance information.


D.

specification.