PMI Certified Associate in Project Management (CAPM) CAPM Question # 59 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 59 Topic 6 Discussion

CAPM Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?


A.

Create a risk in the risk register for each S1 defect and assign actions.


B.

Consult the risk register and implement the risk response actions.


C.

Ask the developers to work longer hours and resolve the defects.


D.

Review the organizational chart to find out who else can sign off UAT.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.