CAPM Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

A tool and technique used during the Define Scope process is:


A.

facilitated workshops.


B.

observations.


C.

questionnaires and surveys.


D.

group creativity techniques.