New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 64 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 64 Topic 7 Discussion

CAPM Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

Which items are components of a project management plan?


A.

Change management plan, process improvement plan, and scope management plan


B.

Agreements, procurement management plan, and work performance information


C.

Schedule management plan, project schedule, and resource calendars


D.

Scope baseline, project statement of work, and requirements traceability matrix


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.