PMI Certified Associate in Project Management (CAPM) CAPM Question # 212 Topic 22 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 212 Topic 22 Discussion

CAPM Exam Topic 22 Question 212 Discussion:
Question #: 212
Topic #: 22

Which items are components of a project management plan?


A.

Change management plan, process improvement plan, and scope management plan


B.

Agreements, procurement management plan, and work performance information


C.

Schedule management plan, project schedule, and resource calendars


D.

Scope baseline, project statement of work, and requirements traceability matrix