The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?


A.

Project charter and stakeholder engagement plan


B.

Risk management plan and stakeholder engagement plan


C.

Communications management plan and stakeholder engagement plan


D.

Project charter and communications management plan