PMI Certified Associate in Project Management (CAPM) CAPM Question # 211 Topic 22 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 211 Topic 22 Discussion

CAPM Exam Topic 22 Question 211 Discussion:
Question #: 211
Topic #: 22

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?


A.

Strong


B.

Weak


C.

Managed


D.

Balanced