Question #: 221
Topic #: 23

What is the most accurate rough order of magnitude (ROM)?


A.

In the Initiation phase, the estimate is in the range of +/- 50%.


B.

In the Planning phase, the estimate is in the range of +/- 50%.


C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.


D.

In the Closing phase, the estimate is in the range of +/- 15%.