Question #: 221
Topic #: 23

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?


A.

Reserve analysis


B.

Three-point estimating


C.

Parametric estimating


D.

Analogous estimating