PMI Certified Associate in Project Management (CAPM) CAPM Question # 220 Topic 23 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 220 Topic 23 Discussion

CAPM Exam Topic 23 Question 220 Discussion:
Question #: 220
Topic #: 23

Progressively elaborating high-level information into detailed plans is performed by the:


A.

project management office


B.

portfolio manager


C.

program manager


D.

project manager


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.