PMI Certified Associate in Project Management (CAPM) CAPM Question # 220 Topic 23 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 220 Topic 23 Discussion

CAPM Exam Topic 23 Question 220 Discussion:
Question #: 220
Topic #: 23

The following is a network diagram for a project.

CAPM Question 220

The shortest non-critical path for the project is how many days in duration?


A.

10


B.

12


C.

14


D.

16


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.