New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 250 Topic 26 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 250 Topic 26 Discussion

CAPM Exam Topic 26 Question 250 Discussion:
Question #: 250
Topic #: 26

What should a project manager use to determine how much money is needed to complete a project?


A.

Earned value management (EVM)


B.

Estimate at completion (EAC)


C.

Earned value analysis (EVA)


D.

Budget at completion (BAG)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.