PMI Certified Associate in Project Management (CAPM) CAPM Question # 249 Topic 25 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 249 Topic 25 Discussion

CAPM Exam Topic 25 Question 249 Discussion:
Question #: 249
Topic #: 25

Inputs to the Plan Schedule Management process include:


A.

Organizational process assets and the project charter,


B.

Enterprise environmental factors and schedule tools.


C.

Time tables and Pareto diagrams.


D.

Activity attributes and resource calendars.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.