PMI Certified Associate in Project Management (CAPM) CAPM Question # 225 Topic 23 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 225 Topic 23 Discussion

CAPM Exam Topic 23 Question 225 Discussion:
Question #: 225
Topic #: 23

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?


A.

Estimate Costs


B.

Control Costs


C.

Plan Cost Management


D.

Determine Budget


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.