Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 201 Topic 21 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 201 Topic 21 Discussion

CAPM Exam Topic 21 Question 201 Discussion:
Question #: 201
Topic #: 21

The following is a network diagram for a project.

CAPM Question 201

The critical path for the project is how many days in duration?


A.

10


B.

12


C.

14


D.

17


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.