New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 215 Topic 22 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 215 Topic 22 Discussion

CAPM Exam Topic 22 Question 215 Discussion:
Question #: 215
Topic #: 22

Which is an example of Administer Procurements?


A.

Negotiating the contract


B.

Authorizing contractor work


C.

Developing the statement of work


D.

Establishing evaluation criteria


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.