PMI Certified Associate in Project Management (CAPM) CAPM Question # 217 Topic 22 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 217 Topic 22 Discussion

CAPM Exam Topic 22 Question 217 Discussion:
Question #: 217
Topic #: 22

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?


A.

Schedule network analysis


B.

Reserve analysis


C.

Alternative analysis


D.

Variance analysis


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.