Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 5 Topic 1 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 5 Topic 1 Discussion

CAPM Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

When is a project finished?


A.

After verbal acceptance of the customer or sponsor


B.

After lessons learned have been documented in contract closure


C.

When the project objectives have been met


D.

After resources have been released


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.