Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 5 Topic 1 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 5 Topic 1 Discussion

CAPM Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?


A.

Rolling wave planning


B.

Expert Judgement


C.

Decomposition


D.

Data analysis


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.