Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 3 Topic 1 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 3 Topic 1 Discussion

CAPM Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

What earned value (EV) measure indicates the cost efficiency of the work completed?


A.

Cost variance (CV)


B.

Cost performance index (CPI)


C.

To-complete performance index (TCPI)


D.

Variance at completion (VAC)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.