Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 47 Topic 5 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 47 Topic 5 Discussion

CAPM Exam Topic 5 Question 47 Discussion:
Question #: 47
Topic #: 5

The three processes of Project Cost Management are:


A.

Estimate Costs, Control Schedule, and Control Costs.


B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.


C.

Determine Budget, Control Schedule, and Estimate Activity Resources.


D.

Estimate Costs, Determine Budget, and Control Costs.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.