New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 16 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 16 Topic 2 Discussion

CAPM Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?


A.

Product


B.

Cost-benefit


C.

Stakeholder


D.

Research


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.