Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 18 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 18 Topic 2 Discussion

CAPM Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?


A.

The project manager should identify and deal with stakeholders only during the execution phase.


B.

Stakeholder satisfaction should be identified immediately and managed as a project objective.


C.

The project manager should focus on project objectives and deal with stakeholders as a secondary priority.


D.

Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.