Big 11.11 Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 43 Topic 5 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 43 Topic 5 Discussion

CAPM Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

Which action is included in the Control Costs process?


A.

Identify how the project costs will be planned, structured, and controlled


B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs


C.

Develop an approximation of the monetary resources needed to complete project activities


D.

Monitor cost performance to isolate and understand variances from the approved cost baseline


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.