Big 11.11 Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 49 Topic 5 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 49 Topic 5 Discussion

CAPM Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:


A.

Available organizational assets


B.

Project staff assignments


C.

Interpersonal skills


D.

Enterprise environmental factors


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.