Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 28 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 28 Topic 3 Discussion

CAPM Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

An input to the Collect Requirements process is the:


A.

stakeholder register.


B.

project management plan.


C.

project scope statement.


D.

requirements management plan.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.