Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 36 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 36 Topic 4 Discussion

CAPM Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

What are the identified risks for doing excessive decomposition in a WBS?


A.

Insufficient project funding and disqualification of sellers


B.

Insufficient project funding and ineffective use of resources


C.

Disqualification of sellers and non-productive management efforts


D.

Non-productive management effort and inefficient use of resources


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.